Author Topic: Park Drive pavement rehabilitation and reconstruction  (Read 13585 times)

0 Members and 3 Guests are viewing this topic.

Offline Wrightwood

  • Administrator
  • Raccoon
  • *****
  • Posts: Plenty of Posts!
  • Wildlife Gateway
Park Drive pavement rehabilitation and reconstruction
« on: Jan 27, 23, 05:50:24 PM »
Subject:    Fwd: County of San Bernardino Board of Supervisors Meeting Agenda - 1/24/23

Note that the Park Drive project has been found exempt from CEQA due to 1. Park Drive is existing facilities and 2. it qualifies are replacement or reconstruction!

APPROVED (CONSENT CALENDAR) Motion/Second: Joe Baca, Jr./Curt Hagman AYE: Col. Paul Cook (Ret.), Jesse Armendarez, Dawn Rowe, Curt Hagman, Joe Baca Jr.

1. Find that the Park Drive and Other Roads Project in the Wrightwood Area is exempt under the California Environmental Quality Act Guidelines, Title 14 of the California Code of Regulations Section 15301(c) Class 1 (existing facilities) and Section 15302(c) Class 2 (replacement or reconstruction).

 2. Approve the Park Drive and Other Roads Project in the Wrightwood Area as defined in the Notice of Exemption and direct the Clerk of the Board of Supervisors to file and post the Notice of Exemption. (Presenter: Brendon Biggs, Director, 387-7906)
-------- Forwarded Message --------
Subject:    County of San Bernardino Board of Supervisors Meeting Agenda - 1/24/23
Date:    Sat, 21 Jan 2023 00:59:47 +0000
From:    San Bernardino County <sbcounty@public.govdelivery.com>
Reply-To:    sbcounty@public.govdelivery.com

Categorical Exemption. State type and section: Class 1 Categorical Exemption Section 15301(c)
Existing Facilities and Class 2, 15302(c) Replacement or Reconstruction

Project Title: Park Dr and Other Roads Project (W.O.H15113)

Project Location: Work is planned for Park Dr from HWY 2
to Apple Ave; Apple Ave from Pine St to Cedar St;
Evergreen Rd from Pine St. to Cedar St. in the community
of Wrightwood in San Bernardino County. See Attachment

2 Location Exhibit.
Project Description: The San Bernardino County Public
Works Department proposes work that generally includes
pavement rehabilitation and reconstruction, new ADA
ramps, sidewalk, curb and gutter and a new concrete
drainage swale. Equipment planned for use on this project
will included but is not limited to: Tractor, asphalt paver,
backhoe, dump truck. No traffic detours or nighttime
construction are planned at this time. Minor relocation of
utilities is anticipated. Construction duration is anticipated
for approximately three (3)-months. County of San
Bernardino Development Code 83.01.80(g)(3): exempts
noise from temporary construction, maintenance, repair, or
demolition activities between 7:00 a.m. and 7:00 p.m.,
except Sundays and Federal holidays
Wrightwood Forum is the first & most dependable local social media outlet

Offline TimG

  • Bear
  • ****
  • Posts: 391
Re: Park Drive pavement rehabilitation and reconstruction
« Reply #1 on: Feb 01, 23, 12:29:10 AM »
How would we find the dates on this?  Worried about it impacting the Ars Festival and Mountaineer Days, etc ...

Offline tlc

  • Bear
  • ****
  • Posts: 307
Re: Park Drive pavement rehabilitation and reconstruction
« Reply #2 on: Feb 01, 23, 01:03:55 AM »
Definitely needs dates asap for event planning. Who would the contact be?

Offline Wrightwood

  • Administrator
  • Raccoon
  • *****
  • Posts: Plenty of Posts!
  • Wildlife Gateway
Re: Park Drive pavement rehabilitation and reconstruction
« Reply #3 on: Feb 01, 23, 01:41:40 AM »
I'd try contacting:
San Bernardino County Public Works Department (909) 387-7910

Offline JP

  • Mouse
  • *
  • Posts: 14
Re: Park Drive pavement rehabilitation and reconstruction
« Reply #4 on: Feb 01, 23, 07:31:28 AM »
A little more info and a map in the docs linked on this page. Looks like they want to solicit bids for construction in spring 2023.
https://sanbernardino.legistar.com/LegislationDetail.aspx?ID=5988735&GUID=4E505012-F7EA-4302-9AE8-9021CB5A9E35&Options=&Search=

Offline TimG

  • Bear
  • ****
  • Posts: 391
Re: Park Drive pavement rehabilitation and reconstruction
« Reply #5 on: Feb 01, 23, 05:24:14 PM »
Thanks, I talked to someone at Public Works, and they said that since it's still out for bids, they have no idea about scheduling yet, or even how long it will take for the Board to approve, and can't even guess a timeline at this point. Bids will presented to the Board in the Spring 2023, but that's all they know.

Offline Wrightwood

  • Administrator
  • Raccoon
  • *****
  • Posts: Plenty of Posts!
  • Wildlife Gateway
Re: Park Drive pavement rehabilitation and reconstruction
« Reply #6 on: Apr 28, 23, 04:52:08 PM »
Any updates

Offline TimG

  • Bear
  • ****
  • Posts: 391
Re: Park Drive pavement rehabilitation and reconstruction
« Reply #7 on: Apr 29, 23, 07:25:40 AM »
Yes, actually, from Paul Cook's office:


4/11/23 - Anticipated Board Approval of the Plans and Specs
7/11/23 - Anticipated Board Approval to Award Construction Contract
8/14/23 to 9/25/23 - Anticipated Start and End of Construction

Whoever sets up the classic car show should get in touch with them any try to put it to later in August?

Offline tlc

  • Bear
  • ****
  • Posts: 307
Re: Park Drive pavement rehabilitation and reconstruction
« Reply #8 on: May 03, 23, 02:59:41 PM »
Thanks Tim. Of course it's the week of the car show. Yikes. I will contact someone.

Offline Wrightwood

  • Administrator
  • Raccoon
  • *****
  • Posts: Plenty of Posts!
  • Wildlife Gateway
Re: Park Drive pavement rehabilitation and reconstruction
« Reply #9 on: Jul 27, 23, 07:57:48 PM »
Construction is anticipated to commence end of August 2023 and be completed by the beginning of October 2023

Bid results: https://www.wrightwoodcalif.com/news/ParkDriveExecutedContract.pdf